Rueter-Hess Reservoir Improvements


Project Description: Marine Diving Solutions provided diving and drilling operations to successfully installed a debris containment log boom giving the intake structure and gates protection from vegetation, logs and loose debris.

Services include:
  • Core drilling 10, six foot holes into the face of the dam to secure 2 sides of the debris containment log boom.
  • Diving to depths up to 120 feet to strategically place 17, 12,000 lbs. anchor blocks in two separate grid locations.
  • MDS assembled the log boom and ran over 700 feet of 1 ½ wire cable to tie it all together.