2025
2023
Project Summary: Marine Diving Solutions mobilized to Stillwater Reservoir near Yampa, Colorado to replace hydraulic lines and perform hydraulic upgrades. The existing hydraulic cylinder lines and vent pipe and supports were removed. MDS provided and installed 3” 316 stainless steel encasement conduit ranging from 6’ to 20’ lengths and installed them within feet downstream of the slide gates and ran the pipe next to the HPU building. MDS also provided and installed flexible hydraulic hose with 316 stainless fittings for the transitions. The existing HPU was replaced with 2 new HPU units and a bypass connection. Hydraulic oil was provided for the hydraulic cylinders, new lines and HPU.
2023/2024
Project Summary: Marine Diving Solutions was awarded this contract to provide and install one hydraulic power unit (HPU) on the 1,337’ elevation level of the intake tower and incorporate the unit both hydraulically and electrically to the existing HPU system. The HPU was to be designed and fabricated to conform to the specifications of the contract as well as be installed into the existing unit on site and tested. Project installation was scheduled for winter months for minimum environmental impact. Due to aging infrastructure of gate cylinders, MDS was issued a modification to our contract for the rehabilitation of E1 gate cylinder.
2023
Winter 2023/2024
2022
2021
2022
2022
2022
2021
2020
2020
2020
Project Summary: Marine Diving Solutions provided the removal of 6 hydraulic cylinders, repairs, and re-installation for the USACE. Additional services included oil testing and filtration.
Services Included:
- ROV inspection underwater
- Bulkhead installation and removal
- Removal and reinstallation of six flanged gate cylinders:
- 200' vertical lift from gate chamber to bridge deck.
- Required to be disassembled prior to lifting.
- 26.5" OD cylinder barrel, 113' long, appx. 5000 lbs each
- 15" long, 5' OD cylinder ram, appx. 1000 lbs each
- All pipe barrels and cylinder rams had to be rotated from vertical to horizontal after lifting, for removal
- Oil filtration and testing
- Working in suspended and fall restriction area
- Modifications including fabrication and welding to the hydraulic operating system piping. Approximately 100' of 1.25" Sched 80 pipe.
2019
Project Summary: Marine Diving Solutions performed commercial diving services at Wolford Dam to remove the existing main gate and install the new owner supplied gate. The trash rack was also removed, coated and re-installed.
Services Included:
2019
Project Description: Marine Diving Solutions provided commercial diving services at Juniata Reservoir to investigate the outlet control valves to see what repairs needed to be done. The trash rack was also removed per the City of Grand Junctions instructions. The North outlet valve assembly was removed at the mid-level outlet so that the City of Grand Junction can purchase new valves and actuators for the future replacement of the outlet valves to control flows out of Juniata Reservoir.
Services Included: