Project Description: Marine Diving Solutions provided fabrication, installation, and rehabilitation services for a 75KG water tower.
Services included:
- Fabrication and installation of a ladder on the exterior of the water tank with landing platforms and wire safety fall arrest systems
- Fabrication and installation of a ladder on the interior of the water tank • Guardrail fabrication and installation on the roof of the water tank
- Removal of a broken 8' by 120' vertical riser pipe removal
- Foundation excavation for a new pipe placement
- Concrete forming and foundation for a new 8' diameter by 130' vertical freestanding ductile iron pipe placement
- Concrete forming and foundation for a new 8' diameter by 130' vertical freestanding ductile iron pipe
- Backfilling and compaction around piping (10' deep)
- Installation of 120' vertical ductile iron pipe
- Fabrication and installation of custom flange to the base of the water tank
- Removal of existing side supports for vertical riser
- Installation of new supports for vertical riser pipe
- Epoxy repairs to corrosion areas due to use on interior of the water tower